Final kitchen pictures.
Finished Pictures: just needs landscaping. Dec 2009.

Kitchen countertops - cabinets in. Awaiting tile floor.
January 26, 2008
Hardwood floors have been installed awaiting sand and fill. Stairway is due to be installed shortly - following that - the floors will be final sanded and sealed. Floor is white oak, 3/4" x 2-1/4" tongue and groove.


December 28, 07': Drywall is completed, stucco has 2nd coat on, and we started interior trim work - doors, closet organizers, casing, window stools, base, crown - and finish electrical has started installing plugs and switches. Paint was applied to the drywall to seal it, and the exterior trim was totally painted prior to the rains.

Drywall has been hung and the 1st and 2nd coats have been applied. Hot mop has been applied to the showers and we await inspection approval to cover with concret and tile. Tile appears to be Travertine throughout the house with a creamy light pattern. Stucco paper and mesh were applied a week ago and the brown coat should be done shortly. Following that, we start placing wood trim on the outside priming and painting it prior to the final coat of color stucco.
Cabinets have been ordered for the kitchen, colors are being selected for the rooms, and prime painting will start after the drywall texture is completed this week.
At the same time, a foundation has been dug for a block wall to replace the front pool wall. Currently awaiting inspection for the trench which was filled with water on the previous rain and inspection day - it was put off to the following week. Blocks have been received and await installation as soon as the foundation is poured.























Once eaves are completed, we can put the windows and doors in.




Sept. 20, 2007: floor joists completed, subfloor 2nd floor installed (95%). Rain on the way! Placed a lot of plastic on existing structure. We hope it goes around us.


We took delivery of our lumber which takes up the whole front yard, plus the dumpster. Trusses come in less than 2 weeks. We're framing the 1st floor now, making changes here and there for doorways (bigger), doors (bigger), and windows (bigger).


Extensive plumbing was done to remove old pipes and bring new copper lines to the existing and new rooms. New gas line, drains, venting, hot and cold water have all been updated.
Total demolition with walls and roof will proceed after the concrete is poured (shortly).
The drawing shows a perspective view of what is being built, with some modifications (French divided lite windows, bigger window in bottom right bedroom). Additional drawings have been provided of the first and second story floor plans. Click on them to enlarge.

August 11, 2007: Demolition progressing, removing flooring and trenching in the middle of the house for 2nd story footings, as well as footing on the outside perimeter. Old clay pipe needs to be replaced for main drain, and extra concrete poured under garage to support the added weight (no bond beam or perimeter footings were ever placed there).
Interior walls have been stripped, plumbing removed, electrical stripped to the bare essentials, and salvaged fixtures removed to other parts on the lot. Three dumpsters filled so far (2 for concrete, one for dirt) and more to come (roofing shingles, dirt, rafters and joists, stucco and windows).

This project involves adding a second story over the center of the house. The roof will be removed over half of the house and the rest will be modified to fit. Also, a garage will be added to the existing garage, extending it 22 ft. The previous garage will be walled off to create a rumpus room.
The exterior walls of the center of the house will be pushed out to provide the large stemwalls needed to hold a second story - that is, new foundation walls will be created as the existing ones are too narrow. In the center of the house, the exiting foundation stemwall will be supported with extra pads of concrete to support the extra load of the second floor. Also, 2 interior walls will also be used for the 2nd story and must be supported with extra concrete.
Overall, the floorplan includes a larger kitchen, dining room, living room, and a bedroom suite downstairs. Upstairs, a master bedroom suite with separate entertainment room, master bath and closet joined together, 2 bedrooms and another bathroom with a stacked laundry system.
Plans call for truss roof framing for the upstairs, and truss joists for the floor/ceiling. The floorplan is unique and flows well into an existing breezeway and family room built previously by the owners. Two furnaces, lots of tile work, all new windows and doors, stucco exterior, dimensional shingle roofing, wood trim, 8ft tall garage door, hardwood flooring downstairs: all new insulation and a whole house attic fan help keep the energy use down in the summer.


